ON-SITE NEUTRALIZATION OF H-6 EXPLOSIVES
  • Client:Confidential Client
  • Site:Former Army Ammunition Plant
  • Date:February 2015

Situation

H-6 (IDP) explosives contamination was present in bulk and residual form on a Melter/Flaker machine within a building. After review of multiple solutions, the client specified the use of MuniRem® Reagent for safe recovery and neutralization of the bulk explosives from the equipment. The photos below show the recovered H-6 (some chunks were 13″ long) and processing with MuniRem®.

Solution

Initial spray application of MuniRem® solution was used to desensitize smaller pieces of the H-6 explosives instantly, enabling for safe ingress/egress for intensive recovery of large H-6 chunks. Under a continuous spray of MuniRem® solution, the staff removed and transported manageable small batches of H-6 bulk material from hopper and tray assemblies to the nearby process area. This explosive material was then neutralized in reaction tanks. Solid and liquid generated waste products were tested for explosives and stored for subsequent transport as non hazardous material.

Result

The project team safely removed hundreds of pounds of bulk explosives from the Melter/Flaker machine.
Although the project plan assumed approximately 200 lbs of H-6 remained on the Melter/Flaker unit, over 900 lbs of bulk explosive material was recovered, including over 950 lbs of solids (sludge and sediment).
Recovery and neutralization of the bulk H-6 enabled dismantling of the Melter/Flaker machine, support structures, conveyor assembly, fume hood, ducts, and wooden platform using hand tools.
The equipment was decontaminated to 5X to enable off-site recycling using the MuniRem® solution alone.
Generated wastewater was characterized and determined to be non-hazardous, achieving regulatory level compliance for final disposition of liquid and solid waste streams for ignitability, corrosivity, reactivity, explosivity, and toxicity.
The project team successfully adapted MuniRem® application practices to overcome unusual inclement weather at Camp Minden, including two days of snow, freezing rain, and multiple days with temperatures below freezing.
Select the fields to be shown. Others will be hidden. Drag and drop to rearrange the order.
  • Image
  • SKU
  • Rating
  • Price
  • Stock
  • Availability
  • Add to cart
  • Description
  • Content
  • Weight
  • Dimensions
  • Additional information
Click outside to hide the comparison bar
Compare